Posted on April 30, 2018 at 8:47 AM by Chris Parrish
Utility work on President Street and General McIntosh Boulevard is mostly complete. Paving crews have moved to East Broad to mill asphalt and relay a new top layer asphalt. The top of the hill on President Street and the area between Truman Parkway and the rail road tracks will be completed next making the surrounding areas blend with the new pavement on President Street and General McIntosh Boulevard. Expect temporary lane closures as crews are finishing up milling, paving and painting lanes. Substantial completion of the project should wrap up in May 2018.