Crews continue to work at the intersection of President Street and the new General McIntosh Blvd in preparation to bore a water main under President Street. This method of installation will allow traffic to remain open on all four lanes without interruption.
On the south side of President Street, crews continue to work on water and sanitary sewer force mains. As this work progresses, the stormwater utility lines are currently being installed in preparation for the next phase that will include a traffic lane shift on President Street.

Stormwater catch basin installation on the south side of President Street.

‘Cribbage’ support for stormwater pipe on the south side of President Street.

‘Cribbage’ support for stormwater pipe on the south side of President Street.

Stormwater catch basin installation on the south side of President Street.

24” Sanitary sewer force main installation on the south side of President Street.

24” Sanitary sewer force main installation on the south side of President Street.