Posted on August 8, 2016 at 8:03 AM by Saja Aures
Stormwater and Water utility lines along the New General McIntosh Blvd are nearing completion.
Crews are currently installing water main casing under General McIntosh Blvd.
On the south side of President Street, surcharge (the area loaded with dirt mounds) removal is complete and crews are working on water and sanitary sewer force mains.

Water main installation along new General McIntosh Blvd.

Water main and casing installation under new General McIntosh Blvd.

Installation of 24” sanitary sewer force main along south side of President St