View All Posts

Oct 02

Oct. 2, 2015 Update

Posted on October 2, 2015 at 3:40 PM by Saja Aures

Wick Drain installations were completed this week on the south side of President Street and along a new section of General McIntosh Boulevard.  Now that wick drains have been installed,  crews have begun to place an additional one foot of course sand over the ends of the wick drains, and will continue with an additional five foot of surcharge backfill material on top of that.  The one foot of course sand material placed prior to wick drain installation, and additional one foot of course sand following wick drain installation will allow the deep underlying ground moisture to wick up to the surface and out of the backfill material, relieving deep underlying soil pore pressure and allowing those underlying soils to consolidate.  This process will continue for an estimated approximately six months.  During that time, the underlying soils are predicted to consolidate to a degree which allows for the surface backfill material to settle up to one and a half feet in some areas.  This process will establish the future adequate foundation necessary for the proposed installation of utility line infrastructure, roadway, and other surface improvements.

Along the new section of Congress Street at General McIntosh Boulevard, crews have installed installed sidewalks, driveways, and ADA compliant handicap ramps. The initial base layer of asphalt will be paved in the next week or two.  Pavement installation is very dependent on weather conditions.  Temperature, absence of rainfall, and proper moisture content of subgrade materials are very important for proper paving conditions.  These conditions will continue to be monitored to determine when paving may occur.

Crews continue to jack and bore steel casings underneath the railroad tracks and future Bilbo Canal, just south of President Street and west of Truman Parkway.  As precise and tedious of a process this is to start with, performing these bores in a twenty plus foot deep excavation within an already low lying area with high ground water (surface water at times) is difficult.  Despite the difficult conditions, the initial 36” steel casing has been completed and the second 36” steel casing installation has begun.

Construction continues on the new reinforced concrete Bilbo Canal walls.  A significant section of the western wall was completed last week, and this week crews have begun preparations necessary to begin installation of the eastern canal wall.  The canal walls will provide for a future 90’ wide open channel canal.  An additional 20’ wide maintenance corridor will be established on either side of the future canal.

100215_Course-Sand-Layer-over-Wick-Drains-on-President-St.jpg

100215_Sidewalk-and-ADA-Ramp-Installation_Congress-St..jpg

100215_Sidewalk-Installation_Congress-at-Gen-McIntosh.jpg

100215_Wick-Drain-Installation_Gen-McIntosh-2.jpg