September 2017 Update



June 2017 Progress Report

Consultant started the preparation of a right-of-way and easement tracking spreadsheet to assist the City Real Property Department to develop a Right-of-Way cost estimate for the project.

Consultant followed up with the Georgia Department of Transportation (GDOT) Office of Environmental Studies on the History Assessment of Effects review status on June 23,  and submitted plan sheets for the project and description modifications, on June 28  for the Memorandum of Agreement between the Federal Highway Administration (FHWA), Georgia Department of Transportation, Georgia Department of Natural Resources Historic Preservation Division, and the City of Savannah.

The Environmental sub-consultant submitted a revised Notification of Intent (NOI) to prepare an Environmental Impact Statement and 4(f) Evaluation; to the Georgia Department of Transportation on June 19, 2017. This document was then forwarded to the Federal Highway Administration on June 23, 2017 for their review and approval.

Consultant prepared a Georgia Department of Transportation Preliminary Field Plan Review checklist with status updates for inclusion in the June 23, 2017 meeting notes.


Additional Project Materials      

Project DeRenne Video Simulation
The portion of Project DeRenne between I-516 and White Bluff Road is known as the Boulevard. This driver’s perspective video simulation allows you to see how it will look upon its completion.





PLEASE SCHEDULE A PROJECT REVIEW SESSION!
For more information, we encourage you to schedule an appointment to review the project in depth by calling Traffic Engineering at (912) 651-6600.