Latest Updates and Project Materials
October 2017 Update
On Wednesday October 25, 2017 the Agency Scoping meeting was held at the Georgia Department of Transportation (GDOT) office in Atlanta. This crucial, and required, step in the NEPA Environmental Impact Assessment (EIS) process invited local, state, and federal agencies to provide input to the project. In addition to representatives from GDOT and the Federal Highway Administration, 8 additional agencies and Native American tribes attended the meeting. These agencies were requested to provide written comments to FWHA within 30 days of the meeting. This input will be included in the design and NEPA analysis for the project.
 
Our next upcoming milestone in the EIS process is holding a Public Scoping meeting. The meeting will be held early 2018. Stay tuned. Additional details will be available soon.


September 2017 Update



June 2017 Progress Report

Consultant started the preparation of a right-of-way and easement tracking spreadsheet to assist the City Real Property Department to develop a Right-of-Way cost estimate for the project.

Consultant followed up with the Georgia Department of Transportation (GDOT) Office of Environmental Studies on the History Assessment of Effects review status on June 23,  and submitted plan sheets for the project and description modifications, on June 28  for the Memorandum of Agreement between the Federal Highway Administration (FHWA), Georgia Department of Transportation, Georgia Department of Natural Resources Historic Preservation Division, and the City of Savannah.

The Environmental sub-consultant submitted a revised Notification of Intent (NOI) to prepare an Environmental Impact Statement and 4(f) Evaluation; to the Georgia Department of Transportation on June 19, 2017. This document was then forwarded to the Federal Highway Administration on June 23, 2017 for their review and approval.

Consultant prepared a Georgia Department of Transportation Preliminary Field Plan Review checklist with status updates for inclusion in the June 23, 2017 meeting notes.


Additional Project Materials      

Project DeRenne Video Simulation
The portion of Project DeRenne between I-516 and White Bluff Road is known as the Boulevard. This driver’s perspective video simulation allows you to see how it will look upon its completion.





PLEASE SCHEDULE A PROJECT REVIEW SESSION!
For more information, we encourage you to schedule an appointment to review the project in depth by calling Traffic Engineering at (912) 651-6600.